§ 10-100. Conceptual mine plan.
The conceptual mine plan shall, at a minimum, contain the following:
(a)
A boundary map depicting the total acreage involved in the project; the proposed annual sequencing of mining and reclamation activities; and the projected life of the mine;
(b)
The planned locations, size, and capacity of future waste storage areas and the estimated heights of their dams;
(c)
The planned location of beneficiation operations;
(d)
A topographical map showing the mine site and its relationship to any watershed;
(e)
A location map of any existing or proposed permanent right-of-ways within the project site;
(f)
The location and identification of all existing and planned facilities and other permanent structures required by the operator in its mining activities within the mining unit covered by the application; and
(g)
A copy of the reclamation and restoration program submitted to the state.
(Ord. No. 88-19, § 3-2, 9-20-88)